Construction of Kaliwa Dam pushed through even without permits – COA

As their forebears have done, the Dumagat traverse the Kaliwa-Agos River in Barangay Magsaysay, Infanta, Quezon, as part of their daily routines. The government is planning to dam the Kaliwa River to make it into an alternative water source for Metro Manila, but the project will mean inundating what the Dumagat consider their ancestral domain. (File photo by RICHARD A. REYES / Philippine Daily Inquirer)

MANILA, Philippines — The construction of the controversial New Centennial Water Source Kaliwa Dam Project (NCWS KDP) was continued even without permits from the appropriate government offices, according to the 2020 audit report of the Commission on Audit (COA).

The Metropolitan Waterworks and Sewerage System (MWSS) is the government agency in charge of the Kaliwa Dam project, which is part of the New Centennial Water Source program that promises to deliver 600 million liters of water per day to Metro Manila.


ADVERTISEMENT

According to COA, this may lead to the cancellation of the Environmental Compliance Certificate (ECC) issued by the Department of Environment and Natural Resources for the project (DENR).

The ECC only allows the MWSS to present measures that will mitigate the impact of the project on community health, welfare, and the environment.

FEATURED STORIES
NEWSINFO


‘No nation deserves him,’ Gordon says of Duterte

NEWSINFO


‘Possible alliance’: Pacquiao’s PDP-Laban faction meets with Partido Reporma

NEWSINFO


‘Bato’ says Duterte ordered him to check Yang’s possible drug links

The MWSS “may only proceed with the project implementation only after it has secured “necessary permits from other pertinent Government agencies,” the COA report said.

The contractor of the $283.2 project is the China Energy Engineering Corp. (CEEC), which has reportedly started the construction of the dam in spite of complaints from indigenous people who will be displaced.

According to COA, the MWSS and its contractor must first comply with the requirements of the National Integrated Protected Areas Systems Act and have a certification issued by the National Commission on Indigenous Peoples. It must also identify disposal sites of excavated materials, among others.

“The ECC is a conditional certificate, where MWSS needs to comply [with] 21 conditions and 4 restrictions that are subject to the approval/evaluation of DENR,” the COA report said.

If the requirements are not met, the COA warned that the ECC could be canceled, which would affect the effectivity of the loan agreement with China Eximbank and the contract with the contractor CEEC.

“We recommended that Engineering and Technical Group secure the necessary permits as required by the DENR for the implmentation of the NCWS KDP and the submission of the Compliance Monitoring ‘Report together with the supporting documents,” the COA said.

In 2019, the government secured a $283.2-million loan deal from China to build the dam, a flagship project under the Build, Build, Build program of President Rodrigo Duterte.


ADVERTISEMENT

The project has generated a lot of criticism, with some people warning that the dam might destroy the ecosystem and the habitat of indigenous people in several Quezon province towns. Others said the deal would be disadvantageous for the country.


READ:

‘Onerous’ provisions of Kaliwa dam project bared

According to Duterte, the project is the “last resort” for Metro Manila’s dwindling water supply.


READ:

Kaliwa dam project gets Duterte’s go-signal

But the studies conducted by the Save Sierra Madre Network Alliance Inc. showed that the dam would end up displacing an estimated 1,465 indigenous families.

Inquirer.net has already reached out to the MWSS but has yet to respond as of posting.


RELATED STORIES



Stop P19-B Kaliwa Dam, groups urge Duterte



House panel OKs resolution stopping Kaliwa Dam project in ancestral domains



Kaliwa Dam deal ‘suspiciously disadvantageous’ to PH



Mishandling of Kaliwa Dam consultation hit


atm

Subscribe to our daily newsletter


Read Next


Some of those who got paid in cash-for-work scheme did not actually work – Bello


EDITORS’ PICK


MOST READ


Don’t miss out on the latest news and information.







View comments